Expansion of Hong Kong International Airport into a Three-Runway System

Construction Phase Monthly EM&A Report No. 3 (For March 2016)

April 2016

Airport Authority Hong Kong

 

 

 

 

 

 

 

 

 

 

 

 

 

 

HKIA Tower, 1 Sky Plaza Road, Hong Kong International Airport, Lantau, Hong Kong

 

 

 

 

 

 

 

 

 

Contents

 

 

Chapter   

Title          Page

Executive Summary  i

1                Introduction  1

1.1______ Background_ 1

1.2______ Scope of this Report 1

1.3______ Project Organisation_ 1

1.4______ Summary of Construction Works 2

1.5______ Summary of EM&A Programme Requirements 2

2                Air Quality Monitoring  5

2.1______ Monitoring Stations 5

2.2______ Monitoring Requirements and Schedule_ 5

2.3______ Monitoring Equipment 5

2.4______ Monitoring Methodology 5

2.5______ Analysis and Interpretation of Monitoring Results 6

3                Noise Monitoring  7

3.1______ Monitoring Stations 7

3.2______ Monitoring Requirements and Schedule_ 7

3.3______ Monitoring Equipment 7

3.4______ Monitoring Methodology 8

3.5______ Analysis and Interpretation of Monitoring Results 9

4                Waste Monitoring  10

4.1______ Monitoring Requirements 10

4.2______ Waste Management Status 10

5                Environmental Site Inspection and Audit 11

5.1______ Weekly Environmental Site Inspection_ 11

5.2______ Audit of Route Diversion and Speed Control of the SkyPier High Speed Ferries 12

5.3______ Ecological Monitoring_ 13

5.4______ Status of Submissions under Environmental Permits 14

5.5______ Compliance with Other Statutory Environmental Requirements 15

5.6______ Analysis and Interpretation of Complaints, Notification of Summons and Status of Prosecutions 15

6                Future Key Issues and Other EIA & EM&A Issues  16

6.1______ Construction Programme for the Coming Reporting Period_ 16

6.2______ Key Environmental Issues for the Coming Reporting Period_ 16

6.3______ Monitoring Schedule for the Coming Reporting Period_ 16

6.4______ Other EIA / EM&A Issues 16

7                Conclusion and Recommendation  17

                 

Tables

Table 1.1:__ Summary of status for all environmental aspects under the Updated EM&A Manual 3

Table 2.1: _ Locations of Impact Air Quality Monitoring Stations 5

Table 2.2: _ Action and Limit Levels for 1-hour TSP_ 5

Table 2.3: _ Air Quality Monitoring Equipment 5

Table 2.4:__ Summary of 1-hour TSP Monitoring Results 6

Table 3.1:__ Locations of Impact Noise Monitoring Stations 7

Table 3.2:__ Action and Limit Levels for Construction Noise_ 7

Table 3.3:__ Noise Monitoring Equipment 8

Table 3.4:__ Summary of Construction Noise Monitoring Results 9

Table 4.1:__ Action and Limit Levels for Construction Waste_ 10

Table 5.1:__ Summary of Key Audit Findings against the SkyPier Plan_ 13

Table 5.2:__ Status of Submissions under Environmental Permit 14

 

 

Figures

Figure 1

Locations of Key Construction Activities in this reporting period

Figure 2

Locations of Air and Noise Monitoring Stations and Chek Lap Kok Wind Station

 

 

Appendices

Appendix A

Environmental Mitigation Implementation Schedule (EMIS) for Construction Phase

Appendix B

Monitoring Schedule

Appendix C

Monitoring Results

Appendix D

Status of Environmental Permits and Licences

Appendix E

Cumulative Statistics on Exceedances, Environmental Complaints, Notification of Summons and Status of Prosecutions

Appendix F

Data of SkyPier HSF Movements to/from Zhuhai and Macau (between 1 and 31 March 2016)

 

 

 

 

 

 


Executive Summary

 

 

 

The “Expansion of Hong Kong International Airport into a Three-Runway System” (the Project) serves to meet the future air traffic demands at Hong Kong International Airport (HKIA).  On 7 November 2014, the Environmental Impact Assessment (EIA) Report (Register No.: AEIAR-185/2014) for the Project was approved and an Environmental Permit (EP) (Permit No.: EP-489/2014) was issued for the construction and operation of the Project.

Airport Authority Hong Kong (AAHK) commissioned Mott MacDonald Hong Kong Limited (MMHK) to undertake the role of Environmental Team (ET) for carrying out the Environmental Monitoring & Audit (EM&A) works during the construction phase of the Project in accordance with the Updated EM&A Manual.

This is the 3rd Construction Phase Monthly EM&A Report for the Project which summarizes the monitoring results and audit findings of the EM&A programme during the reporting period from 1 March 2016 to 31 March 2016.

Key Construction Activities in the Reporting Month

The key construction activities of the Project carried out in the reporting month were related to Contract P560(R) Aviation Fuel Pipeline Diversion Works (Contract P560(R)) which involved site establishment works, construction of temporary concrete footing, mobilization and installation of construction plant, installation of horizontal directional drilling (HDD) casing pipe and setup of site office. Dust suppression measures including wheel washing, watering, covering of excavated materials and establishment of site hoarding have been implemented. Installation of site drainage at the stockpiling area and wastewater treatment facility at the HDD launching site were completed to provide better management of site runoff.

On Sheung Sha Chau Island, topographic survey (including tree and boulder surveys) and installation of safe access facilities (e.g. safety ropes) around the daylighting location were carried out. Measures including prohibiting dumping of waste and effluent as well as tree cutting have been enforced.

 

 

DSC_1032.JPG

Installation of HDD plant at HDD launching site

Installation of safe access facilities around the daylighting location on Sheung Sha Chau Island

 

EM&A Activities Conducted in the Reporting Period

The monthly EM&A programme was undertaken in accordance with the Updated EM&A Manual of the Project. During the reporting period, the ET conducted thirty-six sets of air quality measurements, twenty-five sets of construction noise measurements, one ecological monitoring on Sheung Sha Chau Island as well as five environmental site inspections, landscape & visual and waste monitoring for the Project’s construction works.

 

On the implementation of the Marine Travel Routes and Management Plan for High Speed Ferries of SkyPier (the SkyPier Plan), the situation has been continuously improved in March 2016 by undertaking of ferry movement monitoring audit.  Potential deviations from SkyPier Plan were first identified by the automatic identification system (AIS) monitoring system and notices were issued to concerned ferry operators.  Ferry operators had to provide further information and valid reasons for the deviations.  The deviation cases were reviewed by ET and checked by IEC against the SkyPier Plan.  In March 2016, a total of 822 ferry movements have been monitored and audited.  Three deviations of not fully following the diverted route, one deviation of prevailing speed and thirty-five deviations of instantaneous speed were recorded. Investigation results show that the reasons for deviations included strong local wave, giving ways to other vessels and early acceleration before leaving the SCZ or late deceleration before entering the SCZ. The daily movements of all SkyPier high speed ferries (HSFs) in March 2016 were within the maximum daily cap number. The implementation and monitoring requirements stipulated in the SkyPier Plan were fully complied with.

 

Results of Impact Monitoring

All scheduled 1-hour total suspended particulate (TSP), noise and waste monitoring were completed in the reporting period for the relevant construction activities. No exceedance of the Action/ Limit Levels was recorded.

 

Summary of Upcoming Key Issues

 

Major site activities anticipated in the next reporting period for the Project under Contract P560(R) will include:

 

¡  Construction plant mobilization and installation;

¡  HDD casing pipe installation;

¡  Setup of site office; and

¡  Stockpiling of excavated materials.

 

The key environmental issues will be associated with dust and noise generation, surface runoffs and construction waste management. The implementation of required mitigation measures by the Contractor will be monitored by the ET. No construction works will be carried out on Sheung Sha Chau Island during the ardeid’s breeding season between April and July in accordance with the Updated EM&A Manual.

 

Summary of Other Key Environmental Issues

The progress of other related environmental surveys and baseline monitoring in this reporting month are as follows:

 

On-going:

¡  Baseline monitoring of Chinese White Dolphin (CWD) was on-going during the reporting period; and

 

Fore-coming:

¡  The baseline water quality monitoring programme is scheduled to be commenced in April 2016.

 

Summary Table

 

The following table summarizes the key findings of the EM&A programme during the reporting period from 1 to 31 March 2016:

 

 

Yes

No

Details

Analysis / Recommendation / Remedial Actions

Breaches of Limit Level^

 

ü

No exceedance of project-related limit level was recorded.

Nil

Breaches of Action Level^

 

 

 

ü

No exceedance of project-related action level was recorded.

Nil

Complaints Received

 

ü

No construction activities related complaints were received.

Nil

Notification of any summons and status of prosecutions

 

ü

Neither notifications of summons nor prosecution were received. 

Nil

Changes that affect the EM&A

 

ü

There were no changes to the construction works that may affect the EM&A

Nil

Remarks:                ^ only exceedance of action/ limit level related to Project works will be highlighted. 

 

 


1             Introduction

 

 

 

1.1            Background

 

On 7 November 2014, the Environmental Impact Assessment (EIA) Report (Register No.: AEIAR-185/2014) for the “Expansion of Hong Kong International Airport into a Three-Runway System” (the Project) was approved and an Environmental Permit (EP) (Permit No.: EP-489/2014) was issued for the construction and operation of the Project.

Airport Authority Hong Kong (AAHK) commissioned Mott MacDonald Hong Kong Limited (MMHK) to undertake the role of Environmental Team (ET) for carrying out the Environmental Monitoring & Audit (EM&A) works during the construction phase of the Project in accordance with the Updated EM&A Manual (the Manual) submitted under EP Condition 3.1.  The Manual is available on the Project’s dedicated website (accessible at: http://env.threerunwaysystem.com/en/index.html). AECOM Asia Company Limited (AECOM) was employed by AAHK as the Independent Environmental Checker (IEC) for the Project.

The Project covers the expansion of the existing airport into a three-runway system (3RS) with key project components comprising land formation of about 650 ha and all associated facilities and infrastructure including taxiways, aprons, aircraft stands, a passenger concourse, an expanded Terminal 2, all related airside and landside works and associated ancillary and supporting facilities.  The existing submarine aviation fuel pipelines and submarine power cables also require diversion as part of the works. 

 

Construction of the Project is to proceed in the general order of diversion of the submarine aviation fuel pipelines, diversion of the submarine power cables, land formation, and construction of infrastructure, followed by construction of superstructures. The land-based construction works of the Contract P560(R) Aviation Fuel Pipeline Diversion Works (Contract P560(R)) commenced on 28 December 2015 on the airport island.

All marine works, including the submarine power cable diversion and land formation, will only commence after completion of the gazettal process required under the Foreshore and Sea-bed (Reclamations) Ordinance (FSRO). The overall phasing programme of all construction works and the contract information of Contract P560(R) can be referred to Appendix A of the Construction Phase Monthly EM&A Report No. 1. Any changes/ updates of the construction programme and contract information will be reported in the Monthly EM&A report when necessary.

1.2            Scope of this Report

This is the 3rd Construction Phase Monthly EM&A Report for the Project which summarizes the key findings of the EM&A programme during the reporting period from 1 to 31 March 2016.

1.3            Project Organisation

The Project’s organization structure remained unchanged during the reporting month. The Project’s organization structure and the contact details of the key personnel can be referred to Appendix B and Table 1.1 respectively of the Construction Phase Monthly EM&A Report No.1.

1.4            Summary of Construction Works

During the reporting period, key construction activities of the Project were related to Contract P560(R) Aviation Fuel Pipeline Diversion Works (Contract P560(R)) which involved site establishment works, construction of temporary concrete footing, mobilization and installation of construction plant and installation of horizontal directional drilling (HDD) casing pipe at the HDD launching site located at the west part of the airport.

The erection of site hoarding and installation of site drainage system were completed at the stockpile area located near Chun Ming Road adjacent to Tradeport Logistic Centre on the airport island. Wastewater treatment facility was also installed at the HDD launching site. Site office setup has been continued at a site near the Chek Lap Kok Fire Station at Catering Road East.  Topographic survey (including tree and boulder surveys) and installation of safe access facilities (e.g. safety ropes) were undertaken by the Contractor on Sheung Sha Chau Island.

The HDD launching site and stockpile area are around 3 km and 900 m away respectively from the nearest air and noise sensitive receivers in Tung Chung and the villages in North Lantau. No Construction and Demolition (C&D) material was disposed off-site during the reporting period. The locations of the Contract P560(R) works areas and site office are presented in Figure 1.

 

 

DSC_1032.JPG

Installation of HDD plants at HDD launching site

Installation of safe access facilities around the daylighting location on Sheung Sha Chau Island

 

1.5            Summary of EM&A Programme Requirements

As presented in the Updated EM&A Manual, the environmental aspects of interest for the Project include air quality, noise, water quality, waste management, land contamination, terrestrial ecology, marine ecology, fisheries, landscape & visual, sewage and sewerage, and hazard to human life. 

 

The status for all environmental aspects is presented in Table 1.1. The EM&A requirements remained unchanged during the reporting period and details can be referred to Table 1.2 of the Construction Phase Monthly EM&A Report No. 1.

Table 1.1:      Summary of status for all environmental aspects under the Updated EM&A Manual

Parameters

Status

Air Quality

 

Baseline Monitoring

The baseline air quality monitoring result has been reported in Baseline Monitoring Report (Version 1) and submitted to EPD on 14 December 2015 under EP Condition 3.4.

Impact Monitoring

On-going

Noise

 

Baseline Monitoring

The baseline noise monitoring result has been reported in Baseline Monitoring Report (Version 1) and submitted to EPD on 14 December 2015 under EP Condition 3.4.

Impact Monitoring

On-going

Water Quality

 

General Baseline Water Quality Monitoring for reclamation, water jetting and field joint works

Baseline water quality monitoring programme is scheduled to be commenced in April 2016.

General Impact Water Quality Monitoring for reclamation, water jetting and field joint works

 

To be commenced with the relevant construction works

Initial Intensive Deep Cement Mixing (DCM) Water Quality Monitoring

To be commenced with the relevant construction works

Regular DCM Water Quality Monitoring

To be commenced with the relevant construction works

Waste Management

 

Waste Monitoring

On-going

Land Contamination

 

Supplementary Contamination Assessment Plan (CAP)

To be submitted with the relevant construction works

Contamination Assessment Report (CAR)

To be submitted with the relevant construction works

Terrestrial Ecology

 

Pre-construction Egretry Survey Egretry Survey Plan

A pre-construction egretry survey on Sheung Sha Chau island was conducted between April and July 2015. The Egretry Survey Plan was submitted to EPD on 19 February 2016 under EP Condition 2.14. Subsequent comments on the Egretry Survey Plan were provided by EPD on 3 March 2016. The revised Egretry Survey Plan was submitted to EPD on 18 March 2016.

Ecological Monitoring

The first ecological monitoring of Sha Chau Egretry on Sheung Sha Chau Island was commenced in March 2016.

Marine Ecology

 

Pre-Construction Phase Coral Dive Survey

A pre-construction phase dive survey for corals along the northern and northeastern seawall of the airport island and at the daylighting location on Sheung Sha Chau Island was undertaken and completed on 29 January 2016.

Chinese White Dolphins (CWD)

Vessel survey, land-based theodolite track and passive acoustic monitoring (PAM)

Baseline Monitoring

On-going

Impact Monitoring

To be commenced with the relevant construction works

Landscape & Visual

 

Baseline Monitoring

The baseline landscape & visual monitoring result has been reported in Baseline Monitoring Report (Version 1) and submitted to EPD on 14 December 2015 under EP Condition 3.4.

Impact Monitoring

On-going

Environmental Auditing

 

Regular site inspection

On-going

SkyPier High Speed Ferries (HSF) implementation measures

On-going

Construction and Associated Vessels Implementation measures

To be commenced with the relevant construction works

Complaint Hotline and Email channel

On-going

Environmental Log Book

On-going

Taking into account the nature of the construction works in this reporting month, mainly land-based works of Contract P560(R), the required impact monitoring focused on those environmental aspects including air quality, noise, waste management, landscape & visual and ecology that are relevant to the land-based construction works as recommended in the Updated EM&A Manual.

In addition to air quality, noise, waste, landscape & visual and ecological monitoring, the EM&A programme also involved weekly site inspections and related auditing conducted by the ET for checking the implementation of the required environmental mitigation measures recommended in the approved EIA Report. 

The EM&A programme followed the recommendations presented in the approved EIA Report and the Updated EM&A Manual. A summary of implementation status of the environmental mitigation measures for the construction phase of the Project during the reporting period is provided in Appendix A.

 

2             Air Quality Monitoring

 

 

 

2.1            Monitoring Stations

Air quality monitoring was conducted at two representative monitoring stations in the vicinity of air sensitive receivers in Tung Chung and villages in North Lantau in accordance with the Updated EM&A Manual of the Project. Table 2.1 describes the details of the monitoring stations. Figure 2 shows the locations of the monitoring stations.

Table 2.1:      Locations of Impact Air Quality Monitoring Stations

Monitoring Station

Location

AR1A

Man Tung Road Park

AR2

Village House at Tin Sum

2.2            Monitoring Requirements and Schedule

In accordance with the Updated EM&A Manual, baseline 1-hour total suspended particulate (TSP) levels at the two air quality monitoring stations were established as presented in the Baseline Monitoring Report (Version 1 dated December 2015). Impact 1-hour TSP monitoring was conducted for three times every 6 days. The Action and Limit Levels of the air quality monitoring are provided in Table 2.2. The air quality monitoring schedule involved in the reporting period is provided in Appendix B.

Table 2.2:      Action and Limit Levels for 1-hour TSP

Monitoring Station

Action Level (mg/m3)

Limit Level (mg/m3)

AR1A

306

500

AR2

298

2.3            Monitoring Equipment

Portable direct reading dust meter was used to carry out the 1-hour TSP monitoring.  The brand and model of the equipment are given in Table 2.3.

Table 2.3:      Air Quality Monitoring Equipment

Equipment

Brand and Model                  

Portable direct reading dust meter (Laser dust monitor)

SIBTA LD-3B-002 (Serial No. 974350)

2.4            Monitoring Methodology

2.4.1        Measuring Procedure

The measurement procedure involved in the impact 1-hr TSP monitoring can be summarised as follows: 

a.    The portable direct reading dust meter was mounted on a tripod at a height of 1.2 m above the ground.

b.    Prior to the measurement, the equipment was set up for 1 minute span check and 6 second background check.

c.    The one hour dust measurement was started. Site conditions and dust sources at the nearby area were recorded on a record sheet.

d.    When the measurement completed, the “Count” reading per hour was recorded for result calculation.

2.4.2        Maintenance and Calibration

The portable direct reading dust meter is calibrated every year against high volume sampler (HVS) to check the validity and accuracy of the results measured by direct reading method. The portable direct reading dust meter used in the impact 1-hr TSP monitoring in the reporting month was the same as the one used in the previous reporting month. The corresponding calibration records of the portable direct reading dust meter and the HVS used for calibration provided in Appendix B of the Construction Phase Monthly EM&A Report No.2 are still valid.

2.5            Analysis and Interpretation of Monitoring Results

The monitoring results for 1-hour TSP are summarized in Table 2.4. Detailed impact monitoring results are presented in Appendix C.

Table 2.4:      Summary of 1-hour TSP Monitoring Results

Monitoring Station

1-hr TSP Concentration Range (mg/m3)

Action Level (mg/m3)

Limit Level (mg/m3)

AR1A

40- 248

306

500

AR2

30- 244

298

No exceedance of the Action /Limit Level was recorded at all monitoring stations in the reporting period.

General meteorological conditions throughout the impact monitoring period were recorded. Wind data for each monitoring day including wind speed and wind direction was collected from the Chek Lap Kok Wind Station.

 

3             Noise Monitoring

 

 

 

3.1            Monitoring Stations

Noise monitoring was conducted at five representative monitoring stations in the vicinity of noise sensitive receivers in Tung Chung and villages in North Lantau in accordance with the Updated EM&A Manual of the Project. Figure 2 shows the locations of the monitoring stations and these are described in Table 3.1 below. As described in Section 4.3.3 of the Updated EM&A Manual, monitoring at NM2 will commence when the future residential buildings in Tung Chung West Development become occupied.

Table 3.1:      Locations of Impact Noise Monitoring Stations

Monitoring Station

Location

Type of measurement

NM1A

Man Tung Road Park

Free field

NM2(1)

Tung Chung West Development

To be determined

NM3A

Site Office

Facade

NM4

Ching Chung Hau Po Woon Primary School

Free field

NM5

Village House in Tin Sum

Free field

NM6

House No. 1, Sha Lo Wan

Free field

Note: (1) As described in Section 4.3.3 of the Updated EM&A Manual, noise monitoring at NM2 will only commence after occupation of the future Tung Chung West Development.

3.2            Monitoring Requirements and Schedule

In accordance with the Updated EM&A Manual, baseline noise levels at the noise monitoring stations were established as presented in the Baseline Monitoring Report (Version 1 dated December 2015). Impact noise monitoring was conducted once per week in the form of 30-minute measurements of Leq, L10 and L90 levels recorded at each monitoring station between 0700 and 1900 on normal weekdays. The Action and Limit levels of the noise monitoring are provided in Table 3.2. The construction noise monitoring schedule involved in the reporting period is provided in Appendix B.

Table 3.2:      Action and Limit Levels for Construction Noise

Monitoring Stations

Time Period

Action Level

Limit Level, Leq(30mins) dB(A)

NM1A, NM2, NM3A, NM4, NM5 and NM6

0700-1900 hours on normal weekdays

When one documented

complaint is received from

any one of the sensitive

receivers

 

75 dB(A)(i)

Note: (i) reduce to 70dB(A) for school and 65dB(A) during school examination periods.

3.3            Monitoring Equipment

Noise monitoring was performed using sound level meter at each designated monitoring station.  The sound level meters deployed comply with the International Electrotechnical Commission Publications 651:1979 (Type 1) and 804:1985 (Type 1) specifications.  Acoustic calibrator was used to check the sound level meters by a known sound pressure level for field measurement.  The brand and model of the equipment are given in Table 3.3.

Table 3.3:      Noise Monitoring Equipment

Equipment

Brand and Model

Integrated Sound Level Meter

B&K 2238 (Serial No. 2684503)

B&K 2238 (Serial No. 2800932)

Acoustic Calibrator

B&K 4231 (Serial No. 3003246)

3.4            Monitoring Methodology

3.4.1        Monitoring Procedure

The monitoring procedure involved in the noise impact monitoring can be summarised as follows: 

a.   The sound level meter was set on a tripod at least a height of 1.2 m above the ground for free-field measurements at monitoring stations NM1A, NM4, NM5 and NM6. A correction of +3 dB(A) was applied to the free field measurements.

b.   Façade measurements were made at the monitoring station NM3A.

c.   Parameters such as frequency weighting, time weighting and measurement time were set.

d.   Prior to and after each noise measurement, the meter was calibrated using the acoustic calibrator.  If the difference in the calibration level before and after measurement was more than 1 dB(A), the measurement would be considered invalid and repeat of noise measurement would be required after re-calibration or repair of the equipment.

e.   During the monitoring period, Leq, L10 and L90 were recorded.  In addition, site conditions and noise sources were recorded on a record sheet.

f.    Noise measurement results were corrected with reference to the baseline monitoring levels.

g.   Observations were recorded when high intrusive noise (e.g. dog barking, helicopter noise) was observed during the monitoring.

3.4.2        Maintenance and Calibration

The maintenance and calibration procedures are summarised below:

a.     The microphone head of the sound level meter was cleaned with soft cloth at regular intervals.

b.    The meter and calibrator were sent to the supplier or laboratory accredited under Hong Kong Laboratory Accreditation Scheme (HOKLAS) to check and calibrate at yearly intervals.

The sound level meters and acoustic calibrators used in the noise monitoring in the reporting month were the same as those used in the previous reporting month. The calibration records of the sound level meters and acoustic calibrator provided in Appendix B of the Construction Phase Monthly EM&A Report No.2 are still valid.

 

3.5            Analysis and Interpretation of Monitoring Results

The construction noise monitoring results are summarized in Table 3.4 and the detailed monitoring data are provided in Appendix C.

Table 3.4:      Summary of Construction Noise Monitoring Results

Monitoring Station

Noise Level

Range, dB(A)

Leq (30 mins)

Limit Level, dB(A)

Leq (30 mins)

NM1A(i)

70- 73

75

NM3A

57- 61

75

NM4(i)

64- 66

70(ii)

NM5(i)

53- 59

75

NM6(i)

62- 75

75

Note:       (i) +3 dB(A) Façade correction included;

                (ii) Reduced to 65 dB(A) during school examination periods.  

As the construction activities were small in scale during the reporting period and far away from the monitoring stations, major sources of noise affecting the monitoring stations observed during the construction noise impact monitoring were aircraft noise at NM3A and NM5, aircraft noise and helicopter noise at NM6, road traffic noise at NM1A and school activities at NM4 in this reporting month. 

No exceedance of the Action/ Limit Level was recorded at all monitoring stations in the reporting period.

4             Waste Monitoring

 

 

 

4.1            Monitoring Requirements

In accordance with the Updated EM&A Manual, the waste generated from construction activities was audited at least once per week to determine if wastes are being managed in accordance with the Waste Management Plan (WMP) prepared for the Project, contract-specific WMP, and any statutory and contractual requirements. All aspects of waste management including waste generation, storage, transportation and disposal were assessed during the audits. The Action and Limit levels of the construction waste are provided in Table 4.1.

Table 4.1:      Action and Limit Levels for Construction Waste

Monitoring Stations

Action Level

Limit Level

Construction Area

When one valid documented complaint is

received

Non-compliance of the WMP, contract-specific

WMPs, any statutory and contractual

requirements

4.2            Waste Management Status

Weekly monitoring of the Project construction works were carried out by the ET on 2, 9, 16, 23 and 30 March 2016 to check and monitor the implementation of proper waste management practices during the construction phase.

For Contract P560(R) Aviation Fuel Pipeline Diversion Works, recommendations were provided during monitoring including the removal of oil stain on ground at the stockpiling area on 23 March 2016 and the provision of spill kit and storage of chemical waste at HDD launching site and stockpiling area on 23 and 30 March 2016. The contractor had followed up with implementation of mitigation measures.

The P560(R) Contractor has implemented on-site waste separation by using different waste receptacles as shown in the photo below. The P560(R) Contractor was advised to properly maintain a recording system, maximize the reuse of C&D materials and properly maintain site tidiness.

 

 

 

 

 

 

 

 

 

 

 

 


Colored waste receptacles provided on-site for waste separation

 

 

 

 

 

 

 

 

 

No waste was disposed off-site during the reporting period. No exceedances of the Action and Limit Levels were recorded in the reporting period.

 

5             Environmental Site Inspection and Audit

 

 

 

5.1            Weekly Environmental Site Inspection

Weekly site inspections of the construction works were carried out by the ET on 2, 9, 16, 23 and 30 March 2016 to monitor the implementation of proper environmental pollution control and mitigation measures for the Project. Bi-weekly site inspections were also conducted independently by the Project’s Independent Environmental Checker (IEC) on 2, 16 and 30 March 2016. Observations have been recorded in the site inspection checklist and passed to the Contractor together with the appropriate recommended mitigation measures where necessary.

The key observations from site inspection and associated recommendations were related to the requirements of installation of wheel washing facilities, erection of full hoarding for site boundary and provision of drip tray for oil drum. Dust suppression measures including wheel washing, watering of unpaved site area, covering of excavated materials and establishment of site hoarding have been implemented. The installation of wheel washing facilities at HDD launching site and stockpiling area were in progress.

Installation of site drainage at the stockpiling area and wastewater treatment facility at the HDD launching site were completed to provide better management of site runoff. Installation of mud treatment system for HDD works at the HDD launching site was also in progress. The system will be used for handling the wastewater generated during the drilling process to separate solids and wastewater. The treated water will be reused in the drilling process while the residual solid materials will be stockpiled and reused in the reclamation stage of the Project.

Mitigation measures at HDD launching site and stockpiling area

Installation of wastewater treatment facilities at HDD launching site

Installation of wheel washing facilities at stockpiling area

A summary of implementation status of the environmental mitigation measures for the construction phase of the Project during the reporting period is provided in Appendix A.

5.2            Audit of Route Diversion and Speed Control of the SkyPier High Speed Ferries

The Marine Travel Routes and Management Plan for High Speed Ferries of SkyPier (the SkyPier Plan) has been submitted to the Advisory Council on the Environment (ACE) for comment and subsequently submitted to and approved by EPD in November 2015 under EP Condition 2.10. The approved SkyPier Plan is available on the dedicated website of the Project.  In the SkyPier Plan, AAHK committed to implement the mitigation measure of requiring high speed ferries (HSFs) of SkyPier travelling between HKIA and Zhuhai / Macau to start diverting the route with an associated speed control across an area (i.e. Speed Control Zone (SCZ)) with high Chinese White Dolphin (CWD) abundance by the end of 2015.  The route diversion and speed restriction at the SCZ have been implemented since 28 December 2015.

The situation has been improved in March 2016 by undertaking ferry movement monitoring audit.  Potential deviations from SkyPier Plan were first identified by the monitoring system and notices were issued to concerned ferry operators.  Ferry operators had to provide further information and valid reasons for the deviations.  The deviation cases were reviewed by ET and checked by IEC against the SkyPier Plan. 

 

Key audit findings for the SkyPier HSFs travelling to/from Zhuhai and Macau against the requirements of the SkyPier Plan during the reporting period are summarized in Table 5.1.  The daily movements of all SkyPier HSFs in March 2016 were within the maximum daily cap number. Status of compliance with annual daily average of 99 movements will be further reviewed in the annual EM&A Report. The implementation and monitoring requirements stipulated in the SkyPier Plan were fully complied with. 

 

In total, 822 ferry movements between HKIA SkyPier and Zhuhai / Macau were recorded in March 2016. All SkyPier HSFs had travelled across the SCZ with prevailing speed under 15 knots, except one that travelled at prevailing speed above 15 knots on 5 March 2016. Automatic Identification System (AIS) data obtained for the concerned HSF showed that the instantaneous speed deviated from 15 knots (around 28 knots) for less than 2 minutes when the HSF was entering the SCZ. After that, the HSF had slowed down to around 11 knots for the remaining 6 minutes of the journey within the SCZ. Notice was issued to concerned ferry operator and investigation was conducted. The concerned HSF captain claimed that he was focused on the sea conditions due to numerous small crafts nearby, which led to late deceleration before entering the SCZ. The ferry operator had conducted an internal meeting with the HSF captains immediately after the event. Further trainings will be arranged for the concerned captain to familiarize the exact locations of the entry and exit points of the SCZ.

 

Thirty-five deviation cases of instantaneous speeding across the SCZ have been recorded. Investigation results shown that 30 cases were due to local strong water current. The remaining 5 cases were due to early acceleration before leaving the SCZ or late deceleration before entering the SCZ. Further trainings will be arranged for the concerned captains to familiarize the exact locations of the entry and exit points of the SCZ.

 

Three deviations of HSFs not following the diverted route were recorded on 2 March and 10 March 2016. Notices were sent to the ferry operators and the investigation results are presented as follows: 

¡  One case on 2 March 2016: the HSF captain claimed that he decided to travel outside the SCZ temporarily in order to keep a safe distance from an unknown floating object located within the SCZ. 

¡  Two cases on 10 March 2016: the concerned HSFs were unable to pass through the entry / exit points of the SCZ due to strong tidal wave and adverse weather conditions.

 

Data of SkyPier HSF movements to/from Zhuhai and Macau (between 1 and 31 March 2016) is provided in Appendix F. There were 5 HSF movements with no data signals received by the system on 12 March 2016 and these movements are under investigation.

Table 5.1:      Summary of Key Audit Findings against the SkyPier Plan

Requirements in the SkyPier Plan

1 March to 31 March 2016

Total number of ferry movements recorded and audited

822

Use diverted route and enter / leave SCZ through Gate Access Points

Three deviations

 

 

 

Speed control in speed control zone

1.     One deviation of prevailing speed was recorded on 5 March 2016.

2.     Thirty-five deviations of instantaneous speeding:

≤ 5 knots – 30 cases

> 5 and ≤15 knots – 5 cases (including the deviation case of prevailing speed recorded on 5 March 2016)

 

Daily Cap (including all SkyPier HSFs)

79 to 93 movements (within maximum daily cap)

5.3            Ecological Monitoring

In accordance with the Updated EM&A Manual, ecological monitoring shall be undertaken monthly at the HDD daylighting location on Sheung Sha Chau Island to identify and evaluate any impacts with appropriate actions taken as required to address and minimise any adverse impact found. The first monthly ecological monitoring was carried out by the ET on 19 March 2016 on Sheung Sha Chau Island during which topographic survey (including tree and boulder surveys) and installation of safe access facilities (e.g. safety ropes) were carried out by P560(R) Contractor. The monitoring has confirmed that the works conducted on Sheung Sha Chau Island by P560(R) Contractor had not caused direct encroachment or disturbance to the identified egretry area and that the policies of prohibited dumping of waste and tree cutting had been enforced.

 

A pre-construction egretry survey on Sheung Sha Chau Island conducted between April and July 2015 has indicated that the latest boundary of the egretry had shifted further away from the target daylighting location as shown in the picture below.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

The target daylighting location is located at about 120m away from the nearest boundary of Sha Chau Egretry on Sheung Sha Chau Island

5.4            Status of Submissions under Environmental Permits

The current status of submissions under the EP up to the reporting period is presented in Table 5.2.

Table 5.2:      Status of Submissions under Environmental Permit

EP Condition

Submission

Status

2.1

Complaint Management Plan

Accepted / approved by EPD

 

2.4

Management Organizations

2.5

Construction Works Schedule and Location Plans

2.7

Marine Park Proposal

2.8

Marine Ecology Conservation Plan

2.9

Marine Travel Routes and Management Plan for Construction and Associated Vessels

2.10

Marine Travel Routes and Management Plan for High Speed Ferries of SkyPier

2.11

Marine Mammal Watching Plan

Submitted to EPD

2.13

Fisheries Management Plan

Accepted / approved by EPD

2.14

Egretry Survey Plan

Submitted to EPD

2.15

Silt Curtain Deployment Plan

2.17

Detailed Plan on Deep Cement Mixing

2.16

Spill Response Plan

Accepted / approved by EPD

2.19

Waste Management Plan

3.1

Updated EM&A Manual

3.4

Baseline Monitoring Report

5.5            Compliance with Other Statutory Environmental Requirements

During the reporting period, environmental related licenses and permits required for the construction activities were checked. No non-compliance with environmental statutory requirements was recorded during the reporting period. The environmental licenses, and/or notifications on environmental protection for this Project which approved under this Project during the reporting month are presented in Appendix D.

5.6            Analysis and Interpretation of Complaints, Notification of Summons and Status of Prosecutions

5.6.1        Complaints

During the reporting period, no construction activities related complaints were received.

5.6.2        Notifications of Summons or Status of Prosecution

During the reporting period, neither notifications of summons nor prosecution were received.

5.6.3        Cumulative Statistics

Cumulative statistics on complaints, notifications of summons and status of prosecutions are summarized in Appendix E.

 

6             Future Key Issues and Other EIA & EM&A Issues

 

 

 

 

6.1            Construction Programme for the Coming Reporting Period

Major site activities anticipated in the next reporting period for the Project are expected to be associated with the implementation of the P560(R) Contract and these will include:

¡  Construction plant mobilization and installation;

¡  HDD casing pipe installation;

¡  Setup of site office; and

¡  Stockpiling of excavated materials.

 

No construction works will be carried out on Sheung Sha Chau Island during the ardeids’ breeding season between April and July in accordance with the Updated EM&A Manual.

6.2            Key Environmental Issues for the Coming Reporting Period

The key environmental issues for the Project in the coming reporting period are expected to be associated with the implementation of the P560(R) Contract and these include:

¡  Generation of dust from construction works;

¡  Noise impact from operating equipment and machinery on-site;

¡  Generation of site surface runoffs and wastewater from activities on-site;

¡  Management of stockpiles;

¡  Sorting, recycling, storage and disposal of general refuse and construction waste; and

¡  Management of chemicals and avoidance of oil spillage on-site.

6.3            Monitoring Schedule for the Coming Reporting Period

A tentative schedule of the planned environmental monitoring work in the next reporting period is provided in Appendix B.

6.4            Other EIA / EM&A Issues

6.4.1        On-going and Fore-coming Baseline Monitoring

Baseline monitoring of CWD by vessel surveys, land-based theodolite tracking and passive acoustic monitoring (PAM) are ongoing. The baseline monitoring results will be presented in a separate Baseline Monitoring Report for the marine works.

A baseline water quality monitoring programme is scheduled to be commenced in April 2016.

7             Conclusion and Recommendation

 

 

 

The key construction activities of the Project carried out in the reporting month were related to the Contract P560 Aviation Fuel Pipeline Diversion Works which involved site establishment works, construction of temporary concrete footing, mobilization, installation of construction plants and installation of HDD casing pipe at the HDD launching site. The erection of site hoarding and installation of site drainage system at the stockpile area have been completed.  Dust suppression measures including wheeling washing, watering, covering of excavated materials and establishment of site hoarding have been implemented. Construction of site drainage is also in progress for better management of site runoff. Topographic survey (include tree and boulder surveys) and installation of safe access facilities (e.g. safety ropes) were carried out on Sheung Sha Chau Island. Measures including prohibiting dumping of waste and effluent as well as tree cutting have been enforced.

Construction dust, noise and waste monitoring were carried out in the reporting period. No breach of the Action or Limit Levels in relation to the air quality, construction noise and waste monitoring were recorded in the reporting month.  Monthly ecological monitoring on Sheung Sha Chau Island and weekly site inspections were carried out during the reporting period by the ET. All site observations made by the ET were recorded in the site inspection checklists and passed to the Contractor together with the recommended follow-up actions.

 

On the implementation of the SkyPier Plan, the situation has been continuously improved in March 2016 by undertaking ferry movement monitoring audit. All SkyPier HSFs had travelled across the SCZ with prevailing speed under 15 knots, except one that travelled at prevailing speed above 15 knots.  Three deviations of not following the diverted route, one deviation of prevailing speed and thirty-five deviations of instantaneous speed were recorded. Investigation results shown that the reasons for deviations included strong local wave, giving ways to other vessels and early acceleration before leaving the SCZ or late deceleration before entering the SCZ. The deviation cases were reviewed by ET and checked by IEC against the SkyPier Plan. The daily movements of all SkyPier HSFs in March 2016 were within the maximum daily cap number. The implementation and monitoring requirements stipulated in the SkyPier Plan were fully complied with.